On Wednesday, Maamba Collieries Limited is anticipated to start supplying 150 megawatts of electricity to the national grid once more.
This comes after recent action by President HAKAINDE HICHILEMA, which caused the thermal plant to cut the length of its maintenance interval.
Maamba Collieries Limited is conducting stability tests on Tuesday in preparation for resuming electricity production on Wednesday, according to Energy Minister PETER KAPALA.
According to a statement sent to ZNBC News this afternoon by Mr. KAPALA, Maamba Collieries’ decision to restore its electrical delivery is an effort to lessen the effects of loadshedding on Zambians.
According to Mr. KAPALA, Maamba Collieries Limited began its planned maintenance on January 4 and was intended to finish on January 20.